During the month of September, the exterior of the Center received some polish. The sidewalks and pavers were poured and installed around the building and the new stairs along Poppleton Alley was completed and re-opened to pedestrian traffic.
Inside the building, the proton therapy equipment area received attention with cable trays, light fixtures and pipe installation throughout the month. On the first floor, ceiling grid and plumbing fixtures were completed. Low voltage devices and ceiling tile was installed. Soft flooring and doors and hardware installation also began giving the space shape and form. On the second floor, the ceiling grid and ceiling tile were put in place and flooring installation began as well. On the third floor, drywall hang and finish, prime and the first coat paint was completed and followed by the installation of the ceiling grid, ceramic tile, specialties and plumbing fixtures.